Project date: 2015 - 2016
Services: Project Management, Construction Managment, Cost Consulting
Project owner: DHL Hellas
Location: El. Venizelos Airport, Athens
The DHL's new Gateway Facility at Athens International Airport 'Eletherios Venizelos' covers 5.000 m2 on one level for the warehouse and handling facility, a mezzanine of 1.000 m2 for administration offices and external parking facilities.
Focal was awarded the Project Management. The initial task was the co-ordination of the permit approval from Athens International Airport (AIA). The project management process include the budgeting, managing of the construction tender among experienced contractors, carefully selected and contract assignment. During the construction phase, day to day quality control, co-ordination with FF&E suppliers, contractor’s payments, change order handling, testing and commissioning.